Department of Energy Defense Nuclear Agency Kirtland AFB, New Mexico 87115 COMMENTS ON DRAFT DEMOBILIZATION PLAN FOR ENEWETAK CLEANUP In response to your 20 September letter, this is to provide you with DOE-ERSP comments on the subject draft plan. Any comments that DOE-PASO may have will be furnished separately. William Stanley, DOE-PASO, Honolul DOE PASO Site Rep, Enewetak
Page 2
DOE-ERSP COMMENTS ON DRAFT ENEWETAK DEMOBILIZATION PLAN 1. Our principal comment is to request minor modifications in the redeployment schedules for the USN and USAF personnel assigned to the DOE radiological laboratory. In order to assure the radiological characterization, assessment and certification work is completed by October 1, 1979, assistance of some of the military personnel will be needed for a longer period than presently planned. Accordingly, we request the redeployment schedule be revised as follows: Change date of milestone to 1 July 79 Change Rad Lab Demobilization Schedule as follows: 15 Mar 79 - One person 31 May 79 - One person 1 Aug 79 - One person 15 Ott 79 - One person fl) Change USAF Element to conform with comment l.c.
Page 3
(2) Change USN Element as follows: Final Phaseout (3 persons) - 1 July 79 Change line 17 to read - 4 persons in Apr 79 and - 2 persons in July 79 Change line 18 to read - July 79 Change line 4 to read - End of tour, June 79 Change line 6 to read - End of tour, May 79 Change line 7 to read - End of tour, July 79 ADD : “Any further requirements between June and October 79 will be asTDY.” 2. Page Y-2, line 27 - Change DOE to DOI. Insert new entry to read: “1 Ott 79 - Shutdown and commence demobilization of 4. Page Y-l-H-2, lines 14 and 15 h uncertainty, at presen , is whether or not another phase of soil sampling may be required to deal with Strontium-90 questions. If SO, then the surveyors and draftsman would be needed during that period which should end by June 79 at the latest.
Page 4
Line 17 - Change FRSP to ERSP Paragraph (4)(c) - Any living pattern or activity restriction will not come from ERSP; DOE-Headquarters is responsible for such guidance. Language should be revised to conform with comment #5 above, i.e. DOE-ERSP will provide certification of the radiological conditions of the islands, but DOE-Headquarters is separately responsible for specifying any restrictions in the living or use patterns for inhabitants of the