Operations Plan for Voyage FY 78 #2 to Bikini November 12 Through November 29, 1977

Dated
Oct 26, 1977
Document type
Ops plan(s)
Length
4 pages
Open the original scanArchive record OSTI ID 16378549 · public domain

Document text

Machine-read from the scan, so expect some errors. Lines that couldn’t be read are left out.

Page 1

FOR VOYAGE FY 78 Lawrence Livermore Laboratory (LLL) has established a program in conjunction with DOE to investigate measurement of radionuclides in the soil, water and biota radioecological trans~rt mdeling and dose evaluation in the Marshall Islands. These investigations are to fulfill the high priority needs for effective rehabilitation of affected Marshall Atolls. The Bikini Survey of June 1975 was a follow up effort of DOE to the 1969 Bikini Survey which was accomplished prior to the cleanup and resettlement of Bikini Atoll. Efforts to resettle Bikini Atoll are continuing through the Trust Territory and Marshall District Governments. The purpose of this mission is to continue work on establishing the garden on Eneu Island which was started during the August trip. Samples from the garden will be taken to study the rate of radicmuclide uptake in plants and to provide a program to monitor the resettlement of Bikini and ensure.the safety of the Marshallese currently inhabiting the atoll. Also, work will be done during this trip to establish a base camp to be used on future DESCRIPTION OF MISSION General work to following at Bikini: maintain the garden on Eneu Island and plant additional species of plants as required. Establishment of a drip irrigation system for the garden and build a cover for the catchment pool. Obtain water samples from existing wells for radioecological Collection of water and sediment samples from various Obtain marine life samples for radiological analysis. Collect samples from Work towards setting Collect soil samples any crops that have grown. up permanent camp housing.

Page 2

B. The University of Hawaii personnel will be conducting similar environmental sampling work under the hydrogeochemistry research program. Dr. Robert Buddemeier is the Principal Investigator for this program. A. The Party Chief for this mission is Victor Noshkin, LLL. The Party Chief is responsible for the coordination of overall mission activities with the Captain R. V. Liktanur and while at Bikini, coordinate project with all interested Bikini B. The DOE Coordinator is responsible for ensuring the proper support trailersareon R. V. Liktanur, ensuring that special procurement items at Kwajalein are aboard as well as equipnent shipped from the mainland, supplying a manifest to H&N/PTD for billing purposes at the end of Voyage FY 78 #2 and keeping the PASO staff informed on the status of the mission. c. The PASO staff is responsible for the coordination of this plan with all involved parties prior to publishing; arranging logistical sup~rt in Honolulu and coordinating changes. A. Following is the schedule for the R.V. Liktanur: 11/1 Arrive Kwajalein from previous trip 11/2-11/11 Prepare for Voyage #2 11/12 Depart for Bikini 11/13 or 11/14 Arrive Bikini 11/14-11/26 On station at Bikini 11/28 or 11/29 Arrive Kwajalein B. Following is the schedule for the arrivals and departures

Page 3

ARR DEP ARR DEP ARR DEP ARR ARR NAME ORG. HONO HONO KWAJ KWAJ KWAJ I(WAJ HONO Enewe VI. LOGISTICAL SUPPORT REQUIREMENTS A. The following equipnent is required to be on board for this Backhoe and Dump Truck (to be rented from Martin-Zachary) Gift food for the dri-Bikini Jeep with Trailer Lumber (shipped on barge from Honolulu) 8 Bunk Beds (frames, springs and mattresses) Tent (from Enewetak - to be replaced by buying one in 500 Gal. Diesel Fuel Tank

Page 4

12. Air Sampling Gear (to be shipped from Livermore) 13. Miscellaneous boxes of gear (to be shipped from Livermore) 14. TWO (2) 55 Gal. Drums of Aviation Gas 15. Ten (10) 55 Gal. Drums of Diesel Fuel 16. Five (5) 55 Gal. Drums of Regular Gasoline B. Other PASO supplied logistics include: 1. Entry approval into Kwajalein 2. GSA car reservations and hotel reservations at Outrigger West hotel for days in Honolulu. 3. MAC reservations and travel orders A. LLL efforts have been funded through Request for Services (SANL) No. 609 issued by the University of California Lawrence Livermore Laboratory under USDOE Prime Contract No. W-7405-ENG-48. B. The backhoe and dump truck will be rented from Martin-Zachary at Kwajalein under a purchase order arranged by Holmes & Narver, PTD, and reimbursable by LLL. The backhoe and dump truck will be returned to MZ in the same condition as it was received. In accordance with requirements V., of the “Development of R.V. Likt.~ur Operations Plans” procedure dated September 25, 1975, the Party Chief will submit a report no later than 30 days after completion of the operation to the Director, PASO, with an information copy to the Assistant Manager for Environment & Safety, NV. This report should be concise and cover all pertinent information such as adequacy of support, and offer any comments or recommendations which will improve future operations.